November 5, 2026
The wastewater plant that serves northeast Brunswick County was running at roughly 60% of its physical capacity early this year, according to Port City Daily. By the state's accounting, that same plant is at 127%. Both figures are accurate. The gap between them now matters more than anything else in deciding how much new construction will actually reach the Leland area around Brunswick Forest in the next few years.
Near Brunswick Forest, a planning-board vote no longer tells you when the houses will come. New sewer permits are on hold, and the expansion meant to make room for new projects isn't expected to finish until 2030.
The Northeast Brunswick Regional Water Reclamation Facility in Navassa is jointly owned by Brunswick County and H2GO, the utility that took over Leland's systems. Its numbers look very different depending on what you count.
| Measure | Figure | What it counts |
|---|---|---|
| Physical capacity today | 4.975 million gallons per day | What the plant can treat |
| Actual operating level, early 2026 | About 60% | Flow from homes and businesses already connected |
| Flow promised or connected | About 6.3 million gallons per day | Connected users plus every unbuilt home with a hookup commitment |
| Capacity under the state's calculation | 127% | Promised flow divided by physical capacity |
| Capacity after expansion | 8.725 million gallons per day, about 73% | The same commitments against a larger plant |
The difference comes from Senate Bill 673, a 2023 state law that requires the North Carolina Department of Environmental Quality to count allocated flow, meaning every gallon promised to a future home, as if it were already in the pipes. The state finished the implementing rules in late 2025. For the fastest-growing jurisdictions, the ceiling is 110%, or 115% when an expansion is underway. Every Brunswick County plant is above 115% once anticipated development is included, so DEQ froze new sewer permits at the start of 2026.
County Manager Steve Stone summed up the county's position at a January commissioners' meeting, as Port City Daily reported:
"The yardstick that we've been working under, we really fare favorably. It's the fact that there's a new yardstick that's the issue."
Part of the gap is how the state estimates use. Its rules assume a standard home uses 120 gallons per day per bedroom. Stone said Brunswick's newest homes are averaging closer to 60 or 70. Every unbuilt house on the books is assigned roughly twice the water it is likely to use.
Brunswick County can still approve developments. It cannot commit new sewer hookups until it falls back under the legal threshold, Port City Daily reported in October. Stone has said the freeze is a roadblock rather than a moratorium.
That backlog is already real. A county spokesperson told Port City Daily that about 1.2 million gallons per day, representing roughly 18 developments, was in review or had been submitted during the freeze. In February, the paper reported eight major projects in the northern end of the county were stalled. Stone said then that the county had set a "path forward" for those eight. Each needed a state form, completed by county staff and the developer's engineers, documenting its connection details and accumulated flow.
In practice, the Leland area now runs on two clocks. WilmingtonBiz reported in July that New Leaf Builders had 12 homes under construction in East Lake, with base prices from the mid-$300,000s to the upper $400,000s. Inside Brunswick Forest, H2GO's June 17, 2026 board agenda included a performance guarantee for Phase 9 Section 6, a sign of infrastructure work moving forward in a newer section. Projects still waiting for a new line-extension permit are on the slower clock.
Two large proposals next to Brunswick Forest show how far approvals have moved ahead of hookups.
South Cape. In October 2026, the Brunswick County Planning Board unanimously approved South Cape, a planned development off River Road in Winnabow that borders Mallory Creek and Brunswick Forest. The plan calls for 519 single-family homes and 310 townhomes. Port City Daily's coverage spent much of the meeting on whether South Cape should connect by road to Brunswick Forest Phase 4. A traffic analysis estimated that 65% of Brunswick Forest, roughly 6,700 vehicles a day, would use that road if it opened.
Jackey's Creek. This proposed 1,440-acre community could hold up to 6,000 homes. WilmingtonBiz reported in February that Leland had agreed to annex more than 1,100 acres and approved an $8 million reimbursement agreement for parts of a connector road. The developer requested annexation in order to connect to Leland's utilities, according to Port City Daily.
Combined, that is several thousand homes approved or moving through approval, next to a sewer system that can't commit new flow today. Countywide, Stone has pointed to roughly 48,000 homes approved over the last decade and said they will be built "over a period of decades, not the next three years." Under the new law, though, unbuilt developments with hookup obligations count as if they were already in service.
The Navassa expansion is the main route to new capacity in the system. Based on the October 19 presentation to commissioners, here is the timeline:
The sunset proposal deserves close attention. Commissioner Pat Sykes put it directly at the meeting: "We got projects here that are holding up capacity." If an expiration rule passes, idle allocations could be freed before 2030.
The cost is shared. Developers pay one-time system development fees that cover 75% of plant expansion costs, and current customers pay the other 25% through monthly utility bills.
Cape Fear REALTORS' county report for September 2026 counted 2,477 single-family homes for sale in Brunswick County, essentially unchanged from a year earlier. Months of supply still fell, from 6.4 to 5.3. With flat inventory and shrinking supply, homes are selling faster relative to what is listed. The county logged 448 closed sales and 615 new listings that month, and the median sale price reached $444,953, up 8.5% from September 2025. Days on market rose slightly, to 75 from 73.
The wider Wilmington metro moved more slowly. Cape Fear REALTORS reported a September 2026 median of $423,000, up 4.6% year over year, with 4.48 months of supply.
These figures combine new construction and resale, so they can't show which side is driving the gains. They do show that the county's supply cushion has been shrinking during the same year the sewer freeze took effect. Over the next few years, the new homes available near Brunswick Forest will mostly come from sections whose sewer was committed before 2026. Brunswick Forest itself covers about 4,500 acres, and its published entry points start in the upper $400,000s for move-in-ready new and resale homes and in the upper $100,000s for homesites. Its active builders include Stanley Martin Homes in Trestle Ridge and Legacy Homes by Bill Clark in Collingwood Cottages, and Ibis Roost is a newly planned area.
For a buyer weighing a new home, a homesite or a resale near Brunswick Forest, the planning file tells you less this year than the utility file does. Questions worth asking:
This is general information about public reporting, not legal, financial or engineering advice. The rules and fees above are still changing, so confirm your own situation with the utility provider, your attorney or the right licensed professional before acting.
Is Brunswick County under a building moratorium? No. County officials have said the freeze is not a moratorium. Developments can still be approved, but new sewer hookups can't be committed until capacity falls under the state threshold.
Why is the plant "over capacity" if it isn't physically full? Senate Bill 673 counts flow promised to unbuilt homes as if it were already in use, and state assumptions put each home's water use at about double what the county measures in its newest homes.
When could new hookups resume in the Navassa system? County staff say the expansion will bring the plant down to about 73% of committed capacity, with completion expected in 2030. The county has also been working with the state on project-by-project flow data for stalled permits.
If you're weighing a Brunswick Forest home or homesite against the new communities being planned around it, The Jennifer Farmer Team can help you sort which nearby projects are already building and which are still waiting on sewer, so you can choose with a clear view of the next few years. Open Your Door on the Coast.
Stay up to date on the latest real estate trends.
Whether you're buying, selling, or relocating, we're committed to providing personalized service, trusted guidance, and a real estate experience that turns clients into lifelong friends.